1.

Which of the following is not included in failure costs?

A.  

rework

B.  

repair

C.  

failure mode analysis

D.  

none of the mentioned

2.

Which requirements are the foundation from which quality is measured?

A.  

Hardware

B.  

Software

C.  

Programmers

D.  

None of the mentioned

3.

Which of the following is not a SQA plan for a project?

A.  

evaluations to be performed

B.  

amount of technical work

C.  

audits and reviews to be performed

D.  

documents to be produced by the SQA group

4.

Degree to which design specifications are followed in manufacturing the product is called

A.  

Quality Control

B.  

Quality of conformance

C.  

Quality Assurance

D.  

None of the mentioned

5.

Which of the following is not included in External failure costs ?

A.  

testing

B.  

help line support

C.  

warranty work

D.  

complaint resolution

6.

Which of the following is not an appraisal cost in SQA?

A.  

inter-process inspection

B.  

maintenance

C.  

quality planning

D.  

testing

7.

Who identifies, documents, and verifies that corrections have been made to the software?

A.  

Project manager

B.  

Project team

C.  

SQA group

D.  

All of the mentioned

8.

The primary objective of formal technical reviews is to find _________ during the process so that they do not become defects after release of the software.

A.  

errors

B.  

equivalent faults

C.  

failure cause

D.  

none of the mentioned

9.

What is not included in prevention costs?

A.  

quality planning

B.  

formal technical reviews

C.  

test equipment

D.  

equipment calibration and maintenance

10.

Software quality assurance consists of the auditing and reporting functions of management.

A.  

True

B.  

False